Davis Spring H.O.A. Board Tuesday, October 17, 2017; Time 6:00pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 MEETING NOTES Pool Committee Updates Four Pool Chairs Delivered $800 spent for corner tile repair $1780 spent for kiddie pool flooring repair Lock boxes in place Pool wi-fi – Frank Maulit will try to […]
Author: Frank Maulit
Neenah Construction Update
Progress this Week: Smith Contracting: Continued earthwork for the proposed culvert widening. Began excavation for proposed shared use path (SUP) between Altona Way and Solera Drive. Excavated to verify existing City of Austin (COA) utilities. Began pond improvement work. Two Week Schedule: Smith Contracting: Begin utility adjustments Begin forming concrete floor footing for culvert widening. […]
Wi-Fi at Trailhead Park
The wi-fi has been enabled again at Trailhead Park! Credentials can be found on the website and are subject to change at any time. If you have issues, please let the Davis Spring HOA board know at board@davisspring.org http://www.davisspring.org/resources/trailhead-park-wi-fi/
Neenah Avenue Widening Update
Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor: Smith Contracting Company Anticipated Completion: Spring 2019 Progress this Week: Smith Contracting: Continued clearing the ROW for Phase 1 work. Began embankment work for the proposed culvert widening. Removed the concrete headwall and wingwalls for the proposed culvert widening. Subcontractor Avery Lawn Care continued […]
Neenah Weekly Project Update
Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor: Smith Contracting Company Anticipated Completion: Spring 2019 Progress this Week: Smith Contracting: Continued clearing the ROW for Phase 1 work. Stripped vegetation for embankment work. Subcontractor Avery Lawn Care continued installing erosion control devices for Phase 1 work. Two Week Schedule: Smith Contracting: […]
Davis Spring Open Committee Positions
Greetings Davis Spring neighbors! There are currently several open committee positions that are currently open. We are in need of volunteers to help fill these positions, some of which do not take a lot of commitment, but regardless, help make our neighborhood feel like more of a community. If you are interested in contributing to […]
February 20, 2018 Board Meeting Agenda
Davis Spring H.O.A. Board Tuesday, February 20, 2018; Time 6:00pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 AGENDA Committee Reports Architectural Review Children’s playgroup – Open Garage Sale Landscaping Playground Oak Tree removal Stump removal update Neenah DS Commercial mowing Interest in open position Neighborhood watch – Open Parmer/Neenah Street Light […]
Neenah Weekly Project Update
Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor: Smith Contracting Company Anticipated Completion: Spring 2019 Progress this Week: Smith Contracting: Installed perimeter barricades. Began clearing the ROW for Phase 1 work. Subcontractor Avery Lawn Care began installing erosion control devices for Phase 1 work. Two Week Schedule: Smith Contracting: Complete clearing/grubbing ROW. Begin […]
Neenah Widening Information
Thank you to those who were able to attend the meeting tonight regarding the upcoming construction in our neighborhood. Attached is the slide presentation from Mark Cissell, engineer from the HNTB Corporation who has been our point of contact for the road widening project. Neenah Widening Presentation Some notes from tonight’s meeting not found in […]