Davis Spring 10/17/2017 Board Meeting Notes

Davis   Spring   H.O.A.   Board Tuesday,   October 17,   2017;   Time   6:00pm Real   Manage   Business   Office 9601   Amberglen,   Suite   150 Austin,   TX   78729 MEETING NOTES Pool Committee Updates Four Pool Chairs Delivered $800 spent for corner tile repair $1780 spent for kiddie pool flooring repair Lock boxes in place Pool wi-fi – Frank Maulit will try to […]

Continue reading


Neenah Construction Update

Progress this Week: Smith Contracting: Continued earthwork for the proposed culvert widening. Began excavation for proposed shared use path (SUP) between Altona Way and Solera Drive. Excavated to verify existing City of Austin (COA) utilities. Began pond improvement work. Two Week Schedule: Smith Contracting: Begin utility adjustments Begin forming concrete floor footing for culvert widening. […]

Continue reading


Neenah Avenue Widening Update

Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor:  Smith Contracting Company Anticipated Completion: Spring 2019   Progress this Week: Smith Contracting: Continued clearing the ROW for Phase 1 work. Began embankment work for the proposed culvert widening. Removed the concrete headwall and wingwalls for the proposed culvert widening. Subcontractor Avery Lawn Care continued […]

Continue reading


Neenah Weekly Project Update

Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor:  Smith Contracting Company Anticipated Completion: Spring 2019   Progress this Week: Smith Contracting: Continued clearing the ROW for Phase 1 work. Stripped vegetation for embankment work. Subcontractor Avery Lawn Care continued installing erosion control devices for Phase 1 work.   Two Week Schedule: Smith Contracting: […]

Continue reading


February 20, 2018 Board Meeting Agenda

Davis Spring H.O.A. Board Tuesday, February 20, 2018; Time 6:00pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 AGENDA Committee Reports Architectural Review Children’s playgroup – Open Garage Sale Landscaping Playground Oak Tree removal Stump removal update Neenah DS Commercial mowing Interest in open position Neighborhood watch – Open Parmer/Neenah Street Light […]

Continue reading


Neenah Weekly Project Update

Neenah Avenue Widening (Olive Hill Drive to End) Prime Contractor: Smith Contracting Company Anticipated Completion: Spring 2019 Progress this Week: Smith Contracting: Installed perimeter barricades. Began clearing the ROW for Phase 1 work. Subcontractor Avery Lawn Care began installing erosion control devices for Phase 1 work. Two Week Schedule: Smith Contracting: Complete clearing/grubbing ROW. Begin […]

Continue reading