Neenah Construction Update 3/29/18

Progress this Week: Smith Contracting: Continued placing flexible base for the proposed shared use path (SUP), east of Solera Drive. Completed excavation for the retaining wall footing east of Solera Drive. Placed concrete deck for the 5’x 4’ box culvert extension. Continued excavation and pond improvement work. Placed flexible base for the SUP between Solera […]

Continue reading


Neenah Construction Update 3/16/2018

Progress this Week: Smith Contracting: Continued embankment for the proposed shared use path (SUP), between Altona Way and Solera Drive. Continued excavation for the retaining wall footing east of Solera Drive. Formed/poured concrete for the 5’x 4’ box culvert walls. Connection to the existing waterline pipe for the Church irrigation line was made. Continued pond […]

Continue reading


Neenah Construction Update

Progress this Week: Smith Contracting: Completed earthwork for the culvert extension. Continued excavation for the proposed shared use path (SUP), between Altona Way and Solera Drive. Excavated to verify existing City of Austin (COA) utilities. Continued pond improvement work. Formed/poured the concrete floor of culvert extension. Two Week Schedule: Smith Contracting: Begin utility adjustments. Begin […]

Continue reading