TXDOT has released a survey to gather feedback from concerned commuters who use the stretch of Parmer between SH45 to FM1431. The bond that was passed to widen Parmer Ln. will definitely impact our neighborhood of Davis Spring so it is important that we voice our concerns. https://fm734improvementproject.metroquest.com/ Also, please be reminded that there is […]
Author: Frank Maulit
Social Event Reminder – Thurs. September 27, 2018
We are set to host another Davis Spring HOA Happy Hour on Thursday, Sept 27th from 6-8pm. It will be “come and go” so swing by for a drink or stay and eat with us on the back patio! We will order some pizza and appetizers to share so bring the kids for dinner and […]
Neenah Construction Update – September 21, 2018
Progress this Week: Smith Contracting: Completed excavation for the roadway widening between Solera Drive and the east end of the project. Completed flexible base placement for the shared use path (SUP) between Olive Hill and Altona Way. Began placing flexible base for the roadway widening between Olive Hill and Altona Way. Constructed the southside SUP […]
Parmer Lane Improvements Open House – Tuesday, Sept. 25, 2018
The purpose of the open house is to gather public input on the proposed improvements to FM 734 (Parmer Lane) between RM 1431 and SH 45 North. The meeting will be an open house format so the public may come and go at their convenience, and staff will be available to answer questions. Comments must be […]
Board Meeting Notes – August 21, 2018
Davis Spring H.O.A. Board Tuesday, August 21, 2018; Time 6:30pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 MEETING NOTES Jimmy Flannigan Parmer project on TXDOT plate working w/ Avery Ranch on school traffoc crossings and lights campo money received for widening Lakeline Blvd Commitee reports Landscaping 3 bids for reinvigorating live […]
Trailhead Park Parking Lot Closed for Repairs Thursday
The parking lot at Trailhead Park will be closed for repairs on Thursday, September 20. Any vehicles in the parking lot may be towed in order to perform the repair. The pool, mailboxes, and tennis court should still be accessible, but cars will need to park along Thatcher while the repairs are taking place. We […]
September 18, 2018 Board Meeting Agenda
Davis Spring H.O.A. Board Tuesday, September 18, 2018; Time 6:30pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 AGENDA Committee Reports Architectural Review Children’s playgroup – Open Garage Sale Landscaping Neighborhood watch – Open Playground Inspection status/recommendation Pool Splash pad repair Bathroom survey Social Welcoming Zoning Neenah construction updates Irrigation extension […]
Board Meeting Minutes – July 17, 2018
Davis Spring H.O.A. Board Tuesday, July 17, 2018; Time 6:30pm Real Manage Business Office 9601 Amberglen, Suite 150 Austin, TX 78729 MEETING NOTES In Attendance: Karen McGrath (President), Bob Podnar (Treasurer), Frank Maulit (Secretary), Rocco Pelosi (Landscaping), Barry Merrell (Pool), Robert Borra, Ted Klinker Landscaping Committee Requests for pruning/removal of various trees/vegetation discussed. […]
Neenah Construction Updates – 9/4/2018
Progress this Week: Smith Contracting: Excavated for roadway widening between Altona Way and Solera Drive. Placed topsoil in the ponds. Placed flex base for the shared use path (SUP), between Olive Hill and Altona Way. Began installing pedestrian handrail, on the south side of Neenah along Wall P. Two Week Schedule: Smith Contracting: Continue pond […]
Neenah Construction Updates – August 24, 2018
Progress this Week: Smith Contracting: Formed and placed concrete for guardrail (MBGF) mowstrip in front of Holy Family School. Placed concrete for north side shared use path (SUP) in front of Holy Family School. Excavated for roadway widening and SUP construction between Olive Hill and Altona Way. Two Week Schedule: Smith Contracting: Continue pond improvement […]